Case Studies Archive - ESCO https://escoconsultants.com/abl/case-studies/ The Energy and Marine Consultants Mon, 27 Jan 2025 11:59:37 +0000 en-GB hourly 1 https://wordpress.org/?v=6.7.1 https://escoconsultants.com/abl/wp-content/uploads/2021/04/ESCO-Compass.svg Case Studies Archive - ESCO https://escoconsultants.com/abl/case-studies/ 32 32 MWS for Jeonnam 1 Offshore Wind Project https://escoconsultants.com/abl/case-studies/mws-for-jeonnam-1-offshore-wind-project/ Mon, 27 Jan 2025 11:53:22 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=123379 Project Introduction: Jeonnam 1 is a 96-MW offshore wind farm located off the coast of Shinan County, Jeonnam Province in the southwest of Korea. Comprised of ten wind turbine generators (WTGs), Jeonnam 1 represents the country’s first commercial offshore wind farm. The water depth at the site ranges from 5 to 20 metres, with monopile […]

The post MWS for Jeonnam 1 Offshore Wind Project appeared first on ESCO.

]]>

Client: Jeonnam Offshore Wind Power Corp.

Location: Jeonnam Province, South Korea

Sector: Renewables

Start Date: November 2022

Top-Line Services: MWS: Transportation & Installation, Vessel surveys, inspections & audits

Project Introduction:


Jeonnam 1 is a 96-MW offshore wind farm located off the coast of Shinan County, Jeonnam Province in the southwest of Korea. Comprised of ten wind turbine generators (WTGs), Jeonnam 1 represents the country’s first commercial offshore wind farm.

The water depth at the site ranges from 5 to 20 metres, with monopile foundations featuring monopiles with diameters of up to 8.5m. The wind farm is scheduled to be operational in 2025.

ESCO was appointed as the marine warranty surveyor (MWS) for the transportation and installation (T&I) for the foundations, export cable, inter array cable and wind turbine generator components. The scope of work included providing expert technical reviews, document approvals, vessel inspections and site attendances.

Having successfully completed the installation of the foundations and export/inter array cables, the installation of the first WTG was completed on September 30th 2024. Surveyors from ESCO Korea and ESCO Singapore attended on site to oversee the successful operation.

Project challenges

  • First commercial offshore wind farm project in South Korea required a knowledge transfer of global industry expertise to the local companies.
  • Challenges in establishing operational procedures and methods.
  • Requirement for knowledge and expertise of international jack-up operations standards.

Solutions

  • Providing technical/operational advice based on ESCO’s wide global experience and expertise.
  • ESCO deployed two surveyors during the wind turbine generation installation to ensure that the work was completed without delays including senior expertise from the Singapore office to support with critical points and safety measures.
  • Providing additional advice and support during key points of the jack-up procedures and operations.

Results

  • A secure operation was accomplished through the combined support of ESCO’s Korea and Singapore offices providing engineering support to the project.
  • Streamlined operation and minimised delays on the project schedule with on-site technical review.
  • Upon the successful completion of the first WTG installation, ESCO’s experience and lessons learned on site where communicated to secure all operations for the duration of the project.
  • Installation operations of the last WTG components were completed December 2024

Our value

Group track record supporting South Korea’s offshore wind, contributing to over 8 GW of capacity

Market leading Marine Warranty Survey (MWS) services for offshore wind T&I

“It’s a great honor for ESCO Korea to successfully support the first WTG installation for the JOWP project. We are proud of our involvement in this significant milestone, being the marine warranty surveyor in the first privately held offshore wind development project in Korea.‘’


Junyoung Kim Technical Manager, ESCO Korea

MWS: Renewables

MWS: Renewables

ESCO Consultants is the pre-eminent provider of Marine Warranty Survey (MWS) services for the renewable energy industry, with a particularly strong track record and legacy in supporting offshore wind farm development from the early stages of this technology. We have acted as MWS on over 90 offshore wind farms, both fixed-bottomed and floating, across Europe, […]
Offshore wind turbines and ship

Marine Surveys, Inspections and Audits

ESCO Consultants are world-leading providers in all types of marine surveys, inspections and audits, providing rapid marine assurance and risk support to clients anywhere in the world, and catering to vessels and offshore assets of any type and any size. Clients include vessel owners, managers, charterers, flag state, brokers, banks and insurance parties. Our global […]

The post MWS for Jeonnam 1 Offshore Wind Project appeared first on ESCO.

]]>
Development of Performance Standards for 18 North Sea Oil & Gas Assets https://escoconsultants.com/abl/case-studies/development-of-performance-standards-for-18-north-sea-oil-gas-assets/ Mon, 18 Nov 2024 14:12:13 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=122687 Why ESCO were contracted ESCO are experts with a proven track record in delivering SECE Performance Standards independently or as part of our end-to-end maintenance builds. Our consultants can provide expertise and guidance throughout these projects, from SECE identification, Performance Standards development and the creation and implementation of Performance Standard Assurance Routines. Project overview Due […]

The post Development of Performance Standards for 18 North Sea Oil & Gas Assets appeared first on ESCO.

]]>

Project Objective: To redevelop the client’s SECE (Safety & Environmentally Critical Elements) Performance Standards based on local legislation, international standards and internal requirements.

Client: European Oil & Gas Operator operating within the North Sea

Asset: Offshore Oil & Gas Installations (manned & unmanned

Location: Denmark

Duration: 6 months

Why ESCO were contracted


ESCO are experts with a proven track record in delivering SECE Performance Standards independently or as part of our end-to-end maintenance builds. Our consultants can provide expertise and guidance throughout these projects, from SECE identification, Performance Standards development and the creation and implementation of Performance Standard Assurance Routines.

Project overview

Due to revised internal standards and requirements, the client’s existing Performance Standards were due for revision and presented multiple opportunities for enhancement. These included areas for refinement to ensure;

  • Completeness
  • Alignment with local legislative requirements
  • Synchronisation with the client’s global and international standards

Additionally, there was room for improvement in ensuring alignment with the client’s designated Independent Verification Body (IVB).

What we did

ESCO used the client’s existing performance standards as a foundation to deliver the following 3 steps:

1. Information gathering

  • Collated all relevant information including international standards, client requirements and local legislative requirements
  • This gave us a full understanding of the landscape within which
    our client operates, laying the groundwork for following actions

2. Interactive workshops for collaboration

  • Conducted workshops to engage with the client’s Technical Authorities and designated IVB (Independent Verification Body) to review Performance Standards
  • These interactive sessions facilitated in-depth discussions with stakeholders, creating more informed decision-making

3. Development of Performance Standards

  • Developed a full suite of approximately 95 Performance Standards ready for use
  • The alignment of international best practices with the client’s specific needs supports the client with their operational excellence journey

Key deliverables and benefits

  • The client has a full suite of around 95 Performance Standards, signed off by client Technical Authorities and designated IVB (Independent Verification Body)
  • These Performance Standards:
    • Comply with local legislative requirements
    • Are aligned with the client’s global standards and international standards
    • Are agreed for use by the client’s designated Independent Verification Body (IVB)

“The work ethic, technical knowledge, and level of details from the Engineers attached to the project have been high and the Final Performance Standards are of a high quality.”

Oil and Gas Operator


Process Safety Management Services

Process Safety Management Services

Minimise your project’s exposure to risk with operational risk management from the experts. With decades of experience, our support is tailored to your campaign’s needs.

Process Safety Management (PSM)

Process Safety Management (PSM)

This course will give learners an overview of process safety, risks posed by process hazards and available techniques for managing risks.

Process Safety Audit and Improvement Roadmap for 18 North Sea Oil & Gas Assets

Process Safety Audit and Improvement Roadmap for 18 North Sea Oil & Gas Assets

Why ESCO were contracted ESCO’s Asset Integrity Management (AIM) division has a proven track record of delivering Process Safety solutions globally. Our consultants can provide…


To discuss your Performance Standards or Process Safety Management requirements, fill in the form below and our team will be in touch.

The post Development of Performance Standards for 18 North Sea Oil & Gas Assets appeared first on ESCO.

]]>
Development of Port Marine Personnel Competency Frameworks https://escoconsultants.com/abl/case-studies/port-marine-personnel-competency-frameworks/ Thu, 31 Oct 2024 11:52:35 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=122440 Project overview Our thorough understanding and experience in delivering this type of project as an improvement cycle allowed a rigorous analysis and a robust improvement road map. The road map highlighted the improvement plan, steps for implementation and control. Assessors and Verifiers will now be equipped with validation/evidence based on a recognisable process that is […]

The post Development of Port Marine Personnel Competency Frameworks appeared first on ESCO.

]]>

Project Objective: To supply our client with Personnel Job Competency Profiles aligned with job descriptions and international maritime standards

Client: Ports & Harbours

Location: Nigeria

Project overview

Our thorough understanding and experience in delivering this type of project as an improvement cycle allowed a rigorous analysis and a robust improvement road map. The road map highlighted the improvement plan, steps for implementation and control.

Assessors and Verifiers will now be equipped with validation/evidence based on a recognisable process that is derived from the analysis and implementation plan covering the four focus areas of:

  • ship management;
  • maritime assurance;
  • terminal management;
  • and marine logistics.

This approach addressed any skills dilution that existed.

Challenges faced by the client

The client was experiencing challenges with skills dilution and current job competence profiles not at optimum.

Competency profiles were not aligned to Standards of Training, Certification and Watchkeeping  (STCW), International Harbour Masters Association (IHMA), Safety of Life at Sea (SOLAS), The International Convention for Prevention of Pollution from Ships (MARPOL) and the Oil Companies International Marine Forum (OCIMF) requirements.

What we did

Our scope of work was based on a three-phased approach:

Phase 1

Verify – Propose the controls that should be in place to support the improvement plan.

Define – Programme definition and descriptive problem statement.

Measure – Identify international/national or best practice standards and qualifications across the four focus areas.

Analyse – Carry out a comprehensive gap analysis and generate a report. 

Design – Develop an improvement plan along with suggested controls ready for the next phase of the programme.

Phase 2

Phase 2 was designed to provide implementation, assessment and verification of resources, as a follow on from Phase 1.

Job Competency Profiles covering approximately 40 positions across the four main shipping and marine areas were created.

Verify – Issue report to client for approval.

Define – Expand program definition and refine descriptive problem statement.

Measure – Confirm applicability of international/national or best practice standards and qualifications across the four focus areas. Provide assessment of assessor and verifier profiles.

Analyse – Carry out a gap analysis and generate report for all positions.

Design – Develop an improvement plan along with suggested controls ready for the next phase of the program.

Phase 3

The objective of Phase 3 was to hand over the entire process to the client.

Control – Ensure the designed implementation is being controlled through qualified and/or approved assessors and verifiers.

Implement – Apply designed improvements.

Key elements of an effective Competency Management System

A Competency Management System (CMS) may be quite complex in that competence cannot be assured by a one-off test or examination in a training environment.

Competence describes actual performance in the workplace (or valid simulation of the workplace) over time.

It requires that a person has both the knowledge and the skill to perform a particular function and the ability to apply these to unforeseen circumstances.

Competency develops over time and therefore a competency assurance system should reflect various levels of attainment within any skill area ranging from minimum proficiency through to fully competent.

The value we delivered to the client

Clear and concise job competency profiles aligned with job descriptions.

Detailed implementation road map defining the way forward for individual personnel development.

Adopted widely recognised continuous improvement, define measures, analyse, design and verify methodology.

Job competency profiles aligned with international maritime standards .

Cascading through the awareness, knowledge, skill, and mastery phases of the competency framework.

“The partnership between ESCO’s Asset Integrity Management (AIM) and Maritime teams has led to the successful development of an innovative approach that holds significant potential for global implementation.

By combining our expertise and resources, we have created a model that not only addresses current industry challenges but is also designed to be adaptable and scalable across various international markets.”

ESCO Head of Ports & Harbours Governance

“This collaborative effort showcases a strategic and effective solution that can be widely replicated, offering the potential to drive progress and set new standards on a global level.

We take great pride in the significant achievements and impactful results we have delivered for our client. Our commitment to excellence and dedication to meeting their needs have driven us to consistently provide outstanding solutions.”

ESCO AIM Training Service Manager

Get in touch

To discuss your team competency and how ESCO can support in aligning job descriptions and international maritime standards, fill in the form below and a member of our team will be in touch.

The post Development of Port Marine Personnel Competency Frameworks appeared first on ESCO.

]]>
Equipment Criticality, Risk Matrix, and Performance Standards Alignment https://escoconsultants.com/abl/case-studies/equipment-criticality-risk-matrix-and-performance-standards-alignment/ Tue, 29 Oct 2024 21:40:15 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=122409 Project overview ESCO’s Asset Integrity Management team were contracted to prepare an equipment criticality review process document to be referenced in assessing the criticality of equipment at the client’s bulk storage asset (on site). ESCO also provided all changes to the asset register and criticality scores as an upload file for the client CMMS. The […]

The post Equipment Criticality, Risk Matrix, and Performance Standards Alignment appeared first on ESCO.

]]>

Project Objective: To prepare an equipment criticality review process document to be referenced in assessing the criticality of all equipment at the client’s asset. And to assess and criticality score all maintainable equipment at the asset for upload to the client’s CMMS.

Client: Provider of storage services for bulk liquids and gases

Location: Singapore

Project overview

ESCO’s Asset Integrity Management team were contracted to prepare an equipment criticality review process document to be referenced in assessing the criticality of equipment at the client’s bulk storage asset (on site). ESCO also provided all changes to the asset register and criticality scores as an upload file for the client CMMS.

The project was based on existing asset standards and other applicable local/international standards as well as ESCO’s industry experience. It is expected that the criticality outputs will influence and guide the client’s maintenance function.

A fundamental part of the asset’s operations is effective management of the plant’s technical integrity. To assure this, it is imperative that all safety critical equipment and assets are identified, and the operational, maintenance and inspection routines are defined with the appropriate performance standard tasks.

Equally, to maintain the business obligations to customers at all times, it is important to identify all business critical assets, and put in place effective maintenance that will assure sustained reliability.

Challenges faced by the client

  • The client had previously obtained an equipment criticality analysis from a local source however the outcome and findings were not detailed enough to understand how the classification had been decided.
  • There was no audit trail or reasoning provided from the outsourced equipment criticality analysis to the client which created a vague decision process and low confidence.
  • The client had a risk matrix that required updates with regards to likelihood and severity parameters.
  • The corporate risk matrix procedures parameters required improved alignment with the parameters in the client’s 5×5 risk matrix table.

What we did

  1. ESCO reviewed the scope of the client’s corporate guide document and found it was limited to the definition of the process for assessing equipment criticality within the asset.
  2. Through an iterative process, we explored the best reference parameters for the risk matrix and implemented the improvements to the client’s guide document.
  3. The risk matrix improvement is now contained within the client’s guide document and will provide a basis for future equipment criticality as their prescribed 5 year review cycle indicates.
  4. The process in the guide considers the aspects of Safety, Environmental, Economic and Business impact in determining equipment criticality. The scope also includes the definition of:
    • Safety Critical Equipment (SCE)
    • Safety Critical Asset (SCA)
    • Business Critical Asset (BCA)
    • Provided equipment criticality for all maintainable equipment and reviewed at site with the asset team.


As the project developed, ESCO was contracted to conduct further work scopes that evolved in order to enhance the client’s existing Asset Register.

  • Missing equipment was a specific scope added to capture more recently installed equipment and add to the existing Asset Register.
  • Data cleansing of the existing Asset Register to provide more accurate data and consolidate the equipment class types.

Project deliverables

  • Equipment class types were adjusted to align equipment by strategy at a later date, as part of the continuous improvement cycle over time.
  • Significantly improved client guide document
  • Criticality score for all maintainable equipment documented
  • Addition of missing equipment to the Asset Register
  • Existing Asset Register data cleansed and consolidated

The key project benefits

Consolidating and aligning the risk matrix procedure with the risk matrix improves consistency, efficiency, and accuracy in risk management, leading to better decision-making and enhanced compliance.

By applying generic rules to 80% of equipment class types, the remaining equipment is reviewed in detail with expert input from site personnel influencing the equipment criticality scoring. This enhances efficiency by automating most risk assessments while ensuring critical equipment receives special attention, leading to more accurate and informed risk prioritisation.

A robust risk matrix procedure aligned with the matrix allows for the application of generic rule sets to equipment class types, streamlining risk assessments and standardising processes.

Reviewing equipment criticality scores by exception in a workshop setting fosters team alignment and enhances knowledge sharing, leading to more informed and collaborative decision-making.

Software used for this project: Effio™

Effio™ is ESCO’s cloud-based master data build and optimisation software capable of saving up to 50% on time and cost efficiencies compared to traditional methods. By seamlessly integrating with existing ERP, CMMS and workflows, Effio™ provides a one stop solution for controlled, efficient, consistent, and connected deployment of an asset management strategy.

Effio™ was used across the entire project scope for this client, providing the following benefits:  

  • Centralised data in one place with all changes (including approvals) recorded in the audit log
  • Multi-user access promoting a collaborative working environment between the project team and the client
  • Direct links to drawings for each location within Effio™ using the Library module
  • Automated QA checks for each build category (Locations, Criticality)
  • Automated Criticality calculations within Effio™ for each location
  • Assessed the criticality of all locations as per the client’s criticality matrix, building the ruleset into Effio’s criticality module to ensure auditability of decisions.

To discuss your equipment criticality or asset management requirements, fill in the form below and our team will be in touch.

The post Equipment Criticality, Risk Matrix, and Performance Standards Alignment appeared first on ESCO.

]]>
Yunlin Offshore Windfarm: Marine engineering support for foundation T&I https://escoconsultants.com/abl/case-studies/yunlin-offshore-windfarm-marine-engineering-support-for-foundation-ti/ Fri, 20 Sep 2024 13:22:16 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=121811 Client Challenges Yunneng Wind Power Co. Ltd [A Skyborn, Totalenergies, EGCO Group and Sojitz Corp-led consortium] (formerly WPD) requested ESCO’s support due to several reasons, including: Results ESCO brought several benefits to the project/client: “ESCO’s engineering services in support of the Yunlin OWF is an excellent example of the flexibility and dynamic nature of the […]

The post Yunlin Offshore Windfarm: Marine engineering support for foundation T&I appeared first on ESCO.

]]>

Project title: Yunlin Offshore Windfarm: Marine engineering support for foundation T&I  

Project location: Taiwan

Client: Yunneng Wind Power Co. Ltd [A Skyborn, Totalenergies, EGCO Group and Sojitz Corp-led consortium]

Start date: January 2020 

Assets: 80x Monopile Foundations WTG’s; 640MW total installed capacity

  • Marine Engineering Support for Foundation T&I
  • Marine Advisory

Project Summary:

This 640MW offshore wind farm is in the Taiwan Strait, between 8 and 17 kilometres off the west coast of Taiwan, at water depths from 7 up to 35 meters. The wind farm comprises 80 WTGs, whose generated electricity will be fed into the Taiwanese power grid via two onshore substations, powering nearly 600,000 Taiwanese
households with clean electricity.

This project was uniquely challenging in several ways. For example, the soil conditions in the Taiwan Strait made monopile installation challenging throughout the project and the project’s exposure to extreme natural events, including earthquakes and typhoons, required robust engineering.

Additionally, the main T&I contractor was changed part-way through the project, resulting in significant engineering and methodology changes. However, ESCO was able to continue to support the project throughout this challenging period by driving up the quality of the procedures and engineering throughout the project, reducing the regularity and severity.

Client Challenges

Yunneng Wind Power Co. Ltd [A Skyborn, Totalenergies, EGCO Group and Sojitz Corp-led consortium] (formerly WPD) requested ESCO’s support due to several reasons, including:

  • Extreme environmental conditions (typhoons, etc.)
  • Complex T&I methodology involving a large marine spread and multi-body operations
  • Challenging installation requirements pushing the capabilities of available vessels

Solutions

Detailed engineering studies including:

  • Motions and transportation analyses
  • Feasibility studies
  • Incident support
  • Design of seafastening equipment
  • Development of tow manuals
  • Dynamic mooring analyses
  • Vessel screening studies
  • Rigging/lift plan verification

Technical due diligence in relation to the T&I documents and procedures for the Yunlin offshore wind farm regarding:

  • Safety
  • Operational performance
  • Operational efficiency
  • Good industry practice

ESCO was able to identify and assess gaps and potential risks associated with the planned offshore operations and provide solution-oriented guidance on improvement options for the T&I campaign, drawing upon ESCO’s extensive experience in the construction of offshore wind farms across the globe.

On-site attendance at key moments throughout the project
to provide:

  • Operational office support
  • Completion of vessel surveys, including on/off hire surveys

Results

ESCO brought several benefits to the project/client:

  • Integration of accumulated ESCO knowledge from other projects to enhance the operational efficiency and safety of the foundations T&I campaign
  • Enhanced the clients in-house engineering capabilities, allowing a more robust review of the T&I methodologies proposed by the contractors
  • Office support to enhance safety, efficiency and ensure best practices are adhered to
  • Marine assurance of project vessels and equipment, reducing the likelihood of critical failures and project delay
  • Robust and bespoke engineering analysis carried out in a timely manner

Our Value

Management and document control system for optimised project delivery.

Combined with a long-term legacy in marine assurance and risk.

Largest pool of expertise across energy, marine and engineering disciplines.

“ESCO’s engineering services in support of the Yunlin OWF is an excellent example of the flexibility and dynamic nature of the organisation. By working across time zones and with a diverse set of skilled personnel, ESCO was able to provide robust and timely engineering design and marine assurance services while drawing upon ESCO’s unique global track record to proactively contribute to the success of this exciting project.”

Tilo Klappenbach, Country Manager, ESCO Germany
Offshore wind turbines and ship

Marine Surveys, Inspections and Audits

ESCO Consultants are world-leading providers in all types of marine surveys, inspections and audits, providing rapid marine assurance and risk support to clients anywhere in the world, and catering to vessels and offshore assets of any type and any size. Clients include vessel owners, managers, charterers, flag state, brokers, banks and insurance parties. Our global […]
MWS: Operations

MWS: Operations

The long-term ability of your assets to perform is key to their safe, reliable and profitable operations. Therefore, understanding how your marine assets are ageing gives you the knowledge and ability to better manage your offshore operations and maintenance (‘O&M’) activities to meet your operational and commercial goals. ESCO Consultants combines market-leading marine warranty survey […]

The post Yunlin Offshore Windfarm: Marine engineering support for foundation T&I appeared first on ESCO.

]]>
Process Safety Audit and Improvement Roadmap for 18 North Sea Oil & Gas Assets https://escoconsultants.com/abl/case-studies/process-safety-audit-and-improvement-roadmap-for-18-north-sea-oil-gas-assets/ Wed, 18 Sep 2024 13:59:00 +0000 https://escoconsultants.com/?post_type=case-study&p=122698 Why ESCO were contracted ESCO’s Asset Integrity Management (AIM) division has a proven track record of delivering Process Safety solutions globally. Our consultants can provide expertise and guidance throughout these projects, from Process Safety incident data analysis, interviews with frontline workforce and key stakeholders, to developing improvement action plans and roadmaps to achieve Process Safety […]

The post Process Safety Audit and Improvement Roadmap for 18 North Sea Oil & Gas Assets appeared first on ESCO.

]]>

Project Objective: To assess the client’s current Process Safety performance, particularly relating to Hydrocarbon Releases (HCR), and develop clear Process Safety improvement recommendations in terms of improving both Process Safety culture and the effectiveness of key related processes.

Client: European Oil & Gas Operator operating within the North Sea

Asset: Offshore Oil & Gas Installations (manned & unmanned)

Location: Denmark

Duration: 6 months

Why ESCO were contracted


ESCO’s Asset Integrity Management (AIM) division has a proven track record of delivering Process Safety solutions globally. Our consultants can provide expertise and guidance throughout these projects, from Process Safety incident data analysis, interviews with frontline workforce and key stakeholders, to developing improvement action plans and roadmaps to achieve Process Safety excellence.

Project overview

Process Safety is a key factor in ensuring a safe working environment, our client’s highest priority.

To ensure Process Safety excellence and minimise the risk of Hydrocarbon Releases (HCRs), our client wanted to understand their current Process Safety performance, identify key areas for improvement, and capture and prioritise the associated Improvement Actions into a Process Safety roadmap

What we did

ESCO conducted the Process Safety Improvement project in three phases:

1. Historic Data Analysis

  • Analysis of over 200 safety incident reports using a data model to highlight key Process Safety incident themes in the areas of People, Procedures, Plant and Tools

2. Key Stakeholder Engagement

  • A Process Safety improvement workshop was then held with key client representatives, using the findings from the incident data analysis to engage on Process Safety culture and behaviours

3. Safety & Risk Management Action Plan

  • Process Safety key findings from Phase 1 and 2 were then collated into high level improvement areas, and associated improvement actions developed
  • The improvement actions were then prioritised by the estimated Value vs Effort to identify quick wins and longer term improvement actions

Key deliverables and benefits

From our assessment, ESCO identified;

  • 28 Improvement Areas – specific gaps in Process Safety performance
  • 39 Recommended Actions – key actions recommended to address the improvement areas and achieve Process Safety excellence

Following the above assessment, our client has realised the following benefits;

A quantitative understanding of historical Process Safety incidents and performance

Process Safety Management Services

Process Safety Management Services

Minimise your project’s exposure to risk with operational risk management from the experts. With decades of experience, our support is tailored to your campaign’s needs.

Process Safety Management (PSM)

Process Safety Management (PSM)

This course will give learners an overview of process safety, risks posed by process hazards and available techniques for managing risks.

Development of Performance Standards for 18 North Sea Oil & Gas Assets

Development of Performance Standards for 18 North Sea Oil & Gas Assets

Why ESCO were contracted ESCO are experts with a proven track record in delivering SECE Performance Standards independently or as part of our end-to-end maintenance…

To discuss your Process Safety Management requirements, fill in the form below and our team will be in touch.

The post Process Safety Audit and Improvement Roadmap for 18 North Sea Oil & Gas Assets appeared first on ESCO.

]]>
MWS for Lavrio-Serifos and Serifos-Milos Interconnectors https://escoconsultants.com/abl/case-studies/mws-for-lavrio-serifos-and-serifos-milos-interconnectors/ Thu, 25 Jul 2024 08:31:01 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=120463 Our scope of work ESCO’s scope of work consisted of providing MWS services for the cable load out, shore ends pull-in, laying, offshore jointing, and lay burial, including jetting and trenching. The team of ESCO France performed the work with the support of ESCO Bulgaria for offshore attendance and ESCO Greece for onshore attendance and […]

The post MWS for Lavrio-Serifos and Serifos-Milos Interconnectors appeared first on ESCO.

]]>

Project title: MWS for Lavrio-Serifos and Serifos-Milos Interconnectors  

Project location: Greece

Client: Fulgor Single Member S.A. Hellenic Cable Industry

Start date: October 2023 

Project Summary:

This project is part of Phase D of the interconnection of the Cyclades Islands to the Hellenic Cable Industry Electricity Transmission System. It’s executed by Fulgor Singe Member S.A Hellenic Cable Industry and Asso Subsea as contractors for the end client Hellenic Electricity Distribution Network Operation S.A (HEDNO S.A).

The projects consist of the interconnection of the Islands of Milos and Serifos and of Milos to Lavrio in continental Greece by means of a cable 3x core AC 150 kV XLPE.

The full length of the submarine cable route was approximately 156 km (109 km between Lavrion and Serifos and 47 km between Serifos and Milos), and the maximum sea depth encountered was approximately 500 meters. The cable had an outer diameter of approximately 210 mm.

Our scope of work

ESCO’s scope of work consisted of providing MWS services for the cable load out, shore ends pull-in, laying, offshore jointing, and lay burial, including jetting and trenching. The team of ESCO France performed the work with the support of ESCO Bulgaria for offshore attendance and ESCO Greece for onshore attendance and vessel suitability surveys. Assets involved in the project were CLV Ariadne, TSV Argo, jetting ROV Assojet III and Trencher Assotrencher IV.

Operations took place between two offshore support vessels and four onshore sites. ESCO surveyors were stationed both offshore and onshore for the project’s duration to provide MWS oversight.

In the last five years, ESCO has provided MWS services for Fulgor S.A. on eight occasions.

Client Challenges

Ensure on-site operations for the critical cable pull-in, laying, jointly deployed, and trenching are done in accordance with the approved method statement and documentation.

Expert oversight was needed regarding weather conditions such as wind speeds, sea currents, and significant wave height limits.

Expert oversight of the Health, Safety, and Environmental aspects was required, starting at the documentation approval stage and ending with final implementation on the project site.

Suitability of crucial Offshore Support Vessels for the project prior to commencement.

Solutions

Marine warranty survey (MWS) services covered engineering review, vessel suitability surveys, documentation, and Certificates of Approval provided by ESCO at critical junctures of the project.

Daily Progress Reports documenting operational events observed onboard construction vessels and onshore end worksites and milestones.

Results

Independent oversight ensuring both main contractors are operating in accordance with the approved method statements, prior to and throughout the project duration. Procedures and engineering were thoroughly reviewed, and site surveillance ensured conformity to approved documentations.

ESCO assisted the client in achieving the safest and most efficient execution of the project.

Our Value

Management and document control system for optimised project delivery.

Combined with a long legacy in marine assurance and risk.

Largest pool of expertise across energy, marine and engineering disciplines.

MWS: Project Cargo

MWS: Project Cargo

Across all marine sectors, renewable and oil and gas development projects often require marine transportation of large-scale modular cargo amongst other project-critical and high-value equipment and assets. Loadout, transportation, offloading and discharge operations of warranted project cargo, come with their own set of risks. ESCO Consultants has experience as MWS on all types of project […]
Offshore wind turbines and ship

Marine Surveys, Inspections and Audits

ESCO Consultants are world-leading providers in all types of marine surveys, inspections and audits, providing rapid marine assurance and risk support to clients anywhere in the world, and catering to vessels and offshore assets of any type and any size. Clients include vessel owners, managers, charterers, flag state, brokers, banks and insurance parties. Our global […]
MWS: Operations

MWS: Operations

The long-term ability of your assets to perform is key to their safe, reliable and profitable operations. Therefore, understanding how your marine assets are ageing gives you the knowledge and ability to better manage your offshore operations and maintenance (‘O&M’) activities to meet your operational and commercial goals. ESCO Consultants combines market-leading marine warranty survey […]

The post MWS for Lavrio-Serifos and Serifos-Milos Interconnectors appeared first on ESCO.

]]>
Port-la-Nouvelle: Wet storage solution for floating offshore wind turbines (FOWT) https://escoconsultants.com/abl/case-studies/port-la-nouvelle-wet-storage-solution-for-floating-offshore-wind-turbines-fowt/ Thu, 20 Jun 2024 09:09:38 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=118417 Ports and harbours consulting to support feasible port infrastructure to support France’s floating offshore wind market. Our Scope of Work ESCO’s work was to define the wet storage solutions for 20 MW floating wind turbines inside and outside of the port. The work was divided into two phases. Phase 1 Aimed to define solutions for […]

The post Port-la-Nouvelle: Wet storage solution for floating offshore wind turbines (FOWT) appeared first on ESCO.

]]>

Project title: Port-la-Nouvelle: Wet storage solution for floating offshore wind turbines (FOWT)  

Project location: Port-la-Nouvelle, France

Start date: 2023 

Project Summary:

SEMOP Port-La-Nouvelle and the Occitania Region are investing in port infrastructure with the aim of creating a regional port with the capabilities to accommodate regional and national decarbonization strategies.

This project investigated the suitability of port infrastructure to accommodate floating offshore wind turbines (FOWT), keeping in mind France’s plans for floating wind development in the French Mediterranean Sea.

Ports and harbours consulting to support feasible port infrastructure to support France’s floating offshore wind market.

Our Scope of Work

ESCO’s work was to define the wet storage solutions for 20 MW floating wind turbines inside and outside of the port. The work was divided into two phases.

Phase 1

Aimed to define solutions for each zone. The solutions were then compared through a SWOT matrix to define which ones should be examined in detail.

The solutions considered were:

  • Dolphins inside the port. This solution ticked all the main boxes:
    • Limited space in the port
    • Can accommodate different FOWT designs
    • Low maintenance requirements
  • Standard FOWT mooring outside the port. This solution allows the port to store a large amount of FOWT and can accommodate different FOWT designs

Phase 2

Assessed each solution in detail. This included:

  • Solution detail design and layout
  • Planning includes the engineering of the solution, the procurement and fabrication of different items, and the installation of wet storage. The planning also looks at the permits to be obtained before being able to start the construction
  • Costing of the overall project to help the port to define the CAPEX
  • A method statement defining how to use the wet storage areas
  • Deliverables defining constraints in terms of permits (internal to the port and with French authorities)

The Conclusion

The work required a deep understanding of both port infrastructure and marine operations and expertise in floating offshore wind, from the components to transportation and installation (T&I) operations to future operations and maintenance (O&M) strategies.

With ESCO’s combined energy and marine expertise, we were able to provide a comprehensive service offering and evaluation of wet storage solutions for future FOWT at the port.

Our Value

Mooring design expertise.

Project management expertise.

Maritime legacy and global ports and harbours consultancy.

Floating wind turbine at port

Consulting & Engineering

Offshore structures such as ships, jack-up units, and floating turbines require dedicated marine consultancy services in order to keep them efficient and safe. As experienced marine engineering consultants, we have an entrenched legacy of helping clients to find the right solution for them – achieving sustainable, long-term growth. Marine and engineering consultancy built around your […]

The post Port-la-Nouvelle: Wet storage solution for floating offshore wind turbines (FOWT) appeared first on ESCO.

]]>
Maintenance build for gas treatment plant https://escoconsultants.com/abl/case-studies/maintenance-build-for-gas-treatment-plant/ Fri, 14 Jun 2024 12:39:39 +0000 https://escoconsultants.com/abl/?post_type=case-study&p=118112 Why we were contracted ESCO’s Asset Integrity Management division has a proven track record in delivering successful end-to-end maintenance builds. Our consultants provide expertise and guidance throughout these projects, P&ID extraction of data through to delivering load sheets for the client’s CMMS (SAP in this instance). What we did Asset Hierarchy & Master Equipment List […]

The post Maintenance build for gas treatment plant appeared first on ESCO.

]]>

Project Objective: To ensure critical Plant information, Equipment data, and Maintenance
Tasks and Schedules were identified and uploaded to the CMMS for maintenance to be conducted on the new plant in time for system commissioning and start-up.

Client: Production and development of natural gas assets

Asset: New build Gas Treatment Plant

Location: Iraq

Why we were contracted

ESCO’s Asset Integrity Management division has a proven track record in delivering successful end-to-end maintenance builds. Our consultants provide expertise and guidance throughout these projects, P&ID extraction of data through to delivering load sheets for the client’s CMMS (SAP in this instance).

What we did

Asset Hierarchy & Master Equipment List containing 14,500+ locations & assets

  • Created a Master Equipment List from P&IDs, SLDs and various registers, managing documentation and data using Effio.
  • Developed the Functional Location Hierarchy build using Effio’s hierarchy module, in line with SAP data standards.

Asset Criticality Analysis & Identifications

  • Assessed the criticality of all locations as per the client’s criticality matrix, building the ruleset into Effio’s criticality module to ensure auditability of decisions.
  • Through this process, 2500+ SECE and 4500+ PCE locations were identified.

Asset Maintenance Strategy

  • Determined the Maintenance activities required for all locations to ensure safety and environmental compliance.
  • Work orders were generated at desired frequencies and time using Effio’s maintenance module to optimise production uptime.
  • 13,000+ locations were allocated preventive maintenance routines.

Maintenance Inspection Plan and Checklist

  • Standardised repetitive work processes and checklists which were reviewed and approved by the client in Effio.

BOM, Material Catalogue & Spare Parts Assessment

  • Identified manufacturer and model numbers against assets, before developing and assigning Bills of Materials within Effio.

The key project benefits

Equipment Data Collection and Development

Equipment meta data collection and standardisation for the facility, allows visibility of all locations and simple navigation in SAP (client’s CMMS).

Maintenance Application

Provides on-site technicians with a standardised step-by-step task list for each maintainable item and provides baseline frequencies and durations for each maintenance activity. These task lists can be used from plant commissioning, and can be refined once the plant is running and failure data is captured and analysed.

BoM, Material Catalogue & Spare Parts Assessment

Provides the data to the facility allowing them to house critical spares for equipment. This makes ordering parts and tracking inventory levels more efficient, as all required information has been captured and verified.

Criticality Analysis

Gives the client the ability to prioritise Work Orders and have more control of their maintenance activities and planning.

Software used for this project: Effio™

Effio™ is ESCO’s cloud-based master data build and optimisation software capable of saving up to 50% on time and cost efficiencies compared to traditional methods. By seamlessly integrating with existing ERP, CMMS and workflows, Effio™ provides a one stop solution for controlled, efficient, consistent, and connected deployment of an asset management strategy.

Effio™ was used across the entire project scope for this client, providing the following benefits:  

  • Centralised data in one place with all changes (including approvals) recorded in the audit log
  • Multi-user access promoting a collaborative working environment between the project team and the client
  • The project issue log and document register were controlled within Effio™ 
  • CMMS data standards were built into Effio™ to ensure data compliance when loading
  • Direct links to drawings for each location within Effio™ using the Library module
  • Automated QA checks for each build category (Locations, Criticality, BoMs and Maintenance)
  • Automated Criticality calculations within Effio™ for each location
  • Automated Maintenance Allocation within Effio™ for each location

To discuss your maintenance build or how Effio could support your operations, fill in the form below and our team will be in touch.

The post Maintenance build for gas treatment plant appeared first on ESCO.

]]>